Completed Project : NC 31

Section Name :  Chuli to Maliya (Ch. 63.000 to 120.000 Km)
Package :  Swarnim Gujarat Project
Diameter & Thickness (In MM) :  2000/2150
Transmission :  Pumping
Length :  57.00
Cost In Cr. :  289.00
Operated By :  GWIL
Executed By :  GWIL

Chuli to Maliya (Ch. 63.000 to 120.000 Km)

Salient Features of Project NC-31

Name of Project Dhanki-Maliya (Gravity Main Section) Bulk Water Transmission Pipeline Project
Section Gravity Main Section
Package NC-31
Start Date 31.12.2011
Completion Date 23.07.2013
Pipeline Details Dia of pipe in mm 2000 mm & 2150 mm
Length of pipe in km 32.009 & 25.295 Rmt
Transmission Gravity Section 57.314 Km
pipe carrying capacity In MLD 500 MLD
Details of sump No. of sump NA
Size of sump NA
Capacity of sump NA
Pump house detaile Size of pump house NA
type NA
m3/Hrs NA
Head NA
Number NA
Working NA
Standby NA
pumping capacity 24 Hrs NA
22 Hrs NA

Projects

Previous Next

PROJECT  : NC-38

Section Name :  Upleta to Kutiyana- Ranavav
Package :  NC-38
Diameter & Thickness (In MM) :  800/600
Length :  63.98                  Cost In Cr. :  120.83
Operated By :  GWIL
 

PROJECT  : 300 MLD WSS for Brahmani dam-2 to NC7 PS ( PKG-1)

Section Name :  Brahmani Dam-II to NC-7 Morbi pumping Station
Package :  brahmani Project
Diameter & Thickness (In MM) :  2000
Length :  850.00                  Cost In Cr. :  29.17
Operated By :  GWIL
 

PROJECT  : 300 MLD WSS for Brahmani dam-2 to NC7 PS ( PKG-2)

Section Name :  Brahmani Dam-2 to Chakampar village
Package :  Brahmi Project pkg-2
Diameter & Thickness (In MM) :  2000
Length :  18400.00                  Cost In Cr. :  122.78
Operated By :  GWIL
 

PROJECT  : 300 MLD WSS for Brahmani dam-2 to NC7 PS ( PKG-3)

Section Name :  Chakampar village canal crossing road to Nava sadulka
Package :  brahmani Project pkg-3
Diameter & Thickness (In MM) :  2000
Length :  14600.00                  Cost In Cr. :  100.88
Operated By :  GWIL
 