Completed Project : SPP 3

Section Name :  Navda to Botad
Package :  Saurashtra Pipeline Project
Diameter & Thickness (In MM) :  1650 mm dia
Transmission :  Pumping
Length :  30.90
Cost In Cr. :  57.00
Operated By :  GWIL
Executed By :  GWSSB

Navda to Botad

Salient Features of Project

Name of Project SPP 3
Section Navda-Botad
Start Date Mar-99
Completion Date Jan-01
Pipeline Details Dia of pipe in mm 1650
Length of pipe in km 30.9
Transmission
pipe carrying capacity In MLD 105
Details of sump No. of sump 1 1
Size of sump 15x67x4.2 27x67x4.2
Capacity of sump 11.3 ML
Pump house detaile Size of pump house
type HSCF
m3/Hrs 1200
Head 99
Number 6
Working 4
Standby 2
pumping capacity 24 Hrs 115
22 Hrs 105


Projects

Previous Next

PROJECT  : NC-38

Section Name :  Upleta to Kutiyana- Ranavav
Package :  NC-38
Diameter & Thickness (In MM) :  800/600
Length :  63.98                  Cost In Cr. :  120.83
Operated By :  GWIL
 

PROJECT  : 300 MLD WSS for Brahmani dam-2 to NC7 PS ( PKG-1)

Section Name :  Brahmani Dam-II to NC-7 Morbi pumping Station
Package :  brahmani Project
Diameter & Thickness (In MM) :  2000
Length :  850.00                  Cost In Cr. :  29.17
Operated By :  GWIL
 

PROJECT  : 300 MLD WSS for Brahmani dam-2 to NC7 PS ( PKG-2)

Section Name :  Brahmani Dam-2 to Chakampar village
Package :  Brahmi Project pkg-2
Diameter & Thickness (In MM) :  2000
Length :  18400.00                  Cost In Cr. :  122.78
Operated By :  GWIL
 

PROJECT  : 300 MLD WSS for Brahmani dam-2 to NC7 PS ( PKG-3)

Section Name :  Chakampar village canal crossing road to Nava sadulka
Package :  brahmani Project pkg-3
Diameter & Thickness (In MM) :  2000
Length :  14600.00                  Cost In Cr. :  100.88