Completed Project : SPP 2

Section Name :  Pipli to Navda
Package :  Saurashtra Pipeline Project
Diameter & Thickness (In MM) :  1950 mm dia
Transmission :  Pumping
Length :  40.50
Cost In Cr. :  89.04
Operated By :  GWIL
Executed By :  GWSSB

Pipli to Navda

Salient Features of Project

Name of Project SSP 2
Section PIPLI-NAVDA
Start Date Mar-99
Completion Date Dec-00
Pipeline Details Dia of pipe in mm 1950
Length of pipe in km 40.5
Transmission -
pipe carrying capacity In MLD 250
Details of sump No. of sump 2
Size of sump 45X45X4.20
Capacity of sump 1.6
Pump house detaile Size of pump house -
type HSCF
m3/Hrs 2943
Head 32.5
Number 6
Working 4
Standby 2
pumping capacity 24 Hrs 283
22 Hrs 259


Projects

Previous Next

PROJECT  : NC-38

Section Name :  Upleta to Kutiyana- Ranavav
Package :  NC-38
Diameter & Thickness (In MM) :  800/600
Length :  63.98                  Cost In Cr. :  120.83
Operated By :  GWIL
 

PROJECT  : 300 MLD WSS for Brahmani dam-2 to NC7 PS ( PKG-1)

Section Name :  Brahmani Dam-II to NC-7 Morbi pumping Station
Package :  brahmani Project
Diameter & Thickness (In MM) :  2000
Length :  850.00                  Cost In Cr. :  29.17
Operated By :  GWIL
 

PROJECT  : 300 MLD WSS for Brahmani dam-2 to NC7 PS ( PKG-2)

Section Name :  Brahmani Dam-2 to Chakampar village
Package :  Brahmi Project pkg-2
Diameter & Thickness (In MM) :  2000
Length :  18400.00                  Cost In Cr. :  122.78
Operated By :  GWIL
 

PROJECT  : 300 MLD WSS for Brahmani dam-2 to NC7 PS ( PKG-3)

Section Name :  Chakampar village canal crossing road to Nava sadulka
Package :  brahmani Project pkg-3
Diameter & Thickness (In MM) :  2000
Length :  14600.00                  Cost In Cr. :  100.88
Operated By :  GWIL
 